i) BOC INDUSTRIAL GAS PLANT (Year 1997)
Transported complete Machinery equipment from Karachi Port and Port Qasim to Plan site located in Port Qasim Industrial Zone. The job included following over dimensioned cargoes:
Cold Box
Dimensions: 43 x 4.5 x 3.5 meters
Weight: 125 tons
4 x Storage Tanks
Dimensions: dia 5 x 25 meters
Weight: 87 tons
ii) Gakkhar 500/220/132 KV substation (Year 2007-2008)
We have transported cargo for their substation project at Ghakkhar, Gujranwala, district 1300 km approx. The heavy lifts were upto 127 ton power transformers.
iii) D.H.A. COGEN POWER PLANT (Year 2006 – 2007)
We have transported their power plant project from Karachi Port to DHA, Karachi. The heavy lifts were up to 150 ton packages.